City Rail Link
Drone 9.jpg

Construction updates

Construction updates

 

Latest and previous construction photos are also in our

For stories and photos about the project's progress read our latest (and previous editions) of our

Construction work changes that could affect you are listed in our


17 August 2017

Backfilling starts at Victoria Street shaft

Inside the number one shaft at Victoria St (downhill) shaft, the Connectus team has started backfilling over the new replacement stormwater pipe.

This should be completed by the end of October.

How much is needed? About 2,350m3 which is the equivalence of an Olympic swimming pool. They’re using recycled crushed concrete from a recycling centre in Penrose reducing the trucking which would be required is using quarries in south Auckland.


 

15 August 2017

"Sandrine" starts operating

Sandrine (the nickname of the  bright red machine above)  is a 90 tonne compact hydrofraise piling rig. It's  digging the 15 to 20-metre-deep diaphragm wall (or D-wall) panels that will form the structural support for the CRL tunnels at the CPO / Britomart building .

A D-wall is a continuous wall constructed in the ground, typically to form an underground barrier or structure.

The purpose of the diaphragm walls (D-walls) is to allow the rail tunnels to be constructed by supporting the existing foundations of the Chief Post Office (the underpinning structure will be supported from the D-walls), to provide ground retention during excavation for the rail tunnels and to prevent groundwater ingress into the excavations.

They are constructed through a narrow excavated trench and supported by an engineered fluid (typically a sodium bentonite mud) which is later replaced by permanent concrete.

Sandrine, this hydrofraise HC50 trench-cutter, is lowered through the reinforced concrete guide walls at surface level; as the name suggests the purpose of these walls is guide both the vertical and horizontal alignment of the trench cutter to ensure excavation commences in the correct position. As the trench-cutter moves downwards, its alignment is monitored in ‘real time’ on a computer screen at the HC50’s controls.

At the completion of the works, the diaphragm walls become part of the permanent structure by supporting the CPO building and the CRL tunnel box.

The work will take about six months.

Sandrine is being used by construction partners Downer NZ and Soletanche Bachy JV as they work on the area around the building. 

Soletanche Bachy has a tradition of naming its machinery after women who work for the company.

The rig is named after Sandrine Mussier, who has worked for CRL contractor Soletanche-Bachy for the past 20 years, looking after its international project staff. 


14 August 2017

Road level excavation finishes October

The bulk excavation continues between Wyndham and Swanson Street.  

We are moving the top 1.5 metres of the roadway and placing struts and concrete panels between Swanson Street and Wolfe Street. This will be completed at the end of September.

Road level excavation will be fully completed in Albert Street in October 2017.


8 August 2017

CRL bulk excavation work is challenging- and you can now watch it

The bulk excavation, taking place in Albert Street, is proving challenging work for CRL engineers.

They must construct rail tunnels below groundwater level while maintaining surface-level access to Albert Street for foot and vehicle traffic.

The excavation involves digging 18 metres at the deepest point, using long-reach excavators above ground and smaller machinery inside the reinforced trench. The tunnels will then be constructed with a cast concrete floor, walls and roof before the trench is backfilled.

It represents about 10% of the 3.45km length of the twin-tunnel underground rail link.

The work is being undertaken progressively from Wyndham St at the southern end to Customs St at the northern end.

Excavation at the southern end is expected to be complete by October and the northern by the middle of next year.

Construction of the tunnel box is expected to start late this year and be completed by late 2018. By spring 2019, this section of Albert St will be reinstated with a new road surface, bus lanes, widened footpaths and street furniture.

The bulk excavation marks a significant point in the construction process.

You can watch progress at new viewing windows at the Wyndham Street pedestrian crossing.

Located in the centre of the Albert Street, the north and south-facing windows allow an up-close look at progress on the cut and cover rail tunnel works. Viewing windows are being put in at a Swanson St crossing.

Cut and cover construction is being used at each end of the CRL tunnels – between Britomart Station and the future Aotea Station and, later, where it connects to the western line at Mt Eden. Between Aotea and Mt Eden stations, the tunnels will be between 13 and 42 metres below ground and bored using a 7m diameter tunnel boring machine.

^ back to top


28 July 2017

Capping beams installed

Connectus has finished the installation of 640m of capping beams on top of the 362 piles, connecting them together.

The piles, forming the perimeter of the CRL tunnel box, were installed using a Soilmec SR100 Cased Continuous Flight Auger (CCFA) piling rig over the last six months.

The team can now start the strutting and excavating work for the twin cut and cover tunnels along Albert Street from Customs to Wyndham Streets.

Large steel struts are being installed, spanning between the capping beams to keep the entire structure rigid. All these steps reinforce the trench and support the traffic deck structure during the excavation process.

At a BBQ celebration, Connectus engineer Craig Langsford says it’s a significant achievement. "The capping beam was very heavily reinforced and was completed within tight space and complicated traffic management constraints."

^ back to top


23 July 2017

First concrete poured

The first two concrete base slabs for the CRL twin-tunnels have been laid on Lower Queen Street.

The 700mm-thick concrete slabs are the first eight metres of CRL tunnel box floor to be poured out of the total 3.45km length of tunnel to be constructed.

Located under the Lower Queen Street walkway, adjacent to the Zurich building, these tunnel stubs will eventually connect to sections of tunnel from Britomart Station and Albert Street.

The slabs are protected by a high-tech water-proofing system to keep saltwater out, as they’re sitting about 13 metres below sea level.

In about a week, construction will start on the walls for this short section of tunnel. When a roof is eventually placed over the top in few month’s time, the result will be the first completed section of tunnel box for the project.

^ back to top


19 July 2017

Project Director discusses what's happening downtown

CRL Project Director Chris Meale discusses the current construction happening downtown.


17 July 2017

The Big Dig starts

Bulk excavation work has started for the cut and cover rail tunnels under Albert Street.

The excavation involves digging 18 metres (about five storeys) at the deepest (southern) point, using long-reach excavators above ground and smaller machinery inside the reinforced trench.

The work will be undertaken progressively from Wyndham St at the southern end to Customs Street at the northern end.

Excavation at the southern end is expected to be completed by October this year and the northern end by the middle of next year. 

This represents about 10% of the 3.45km length of the twin-tunnel underground rail link.

The tunnels will then be constructed with a cast concrete floor, walls and roof before the trench is backfilled.

^ back to top


5 July 2017

Then there were six!

Those impressive-looking giant red silos outside the Britomart Transport centre have doubled in number - from three to six.

The three complete the set-up of the plant, which will remain on site until early 2018.

They will fulfil an important task in preparing the building for CRL tunnel excavation.  


5 July 2017

Here's a puzzle

How is this for a puzzle for those preparing for the tunnel construction! This is a map they've made of the utilities (like power lines) under the intersection of Victoria and Albert Streets.

Utilities Albert and Victoria.jpg

3 July 2017

Birds eye view

Here's a birds eye view of the construction outside the Britomart Transport centre (old CPO building) today.

Scroll down further to see more commentary on what is happening. The silos are part of a specialised bentonite plant, shipped over from France by CRL contractor Downer Soletanche-Bachy Joint Venture, to help with the construction of diaphragm walls that will support the CPO building foundations and the CRL tunnel box.  Sodium Bentonite is an absorbent clay that expands when wet. In civil engineering applications bentonite is used as a mineral hydraulic barrier in diaphragm walls, foundations, tunnelling, horizontal directional drilling and pipe jacking.

^ back to top


30 June 2017

Galway service trench work almost complete

The 3.5m-deep utility services trench constructed on Galway Street is almost complete.

The trench was constructed to allow re-routing of existing underground services that would otherwise clash with CRL tunnel extension work at Britomart Station.

Pre-cast concrete panels have been placed over the top of the trench and a structural topping will shortly be applied to form a concrete slab lid for the trench.

Next week the temporary structures that were used to stabilise the soil either side of the trench during its construction, will be removed.

A new water treatment plant will be installed in Galway Street on 10 July.

^ back to top


29 June 2017

Steel supports and traffic deck installed on Albert Street

On Albert St, between Wyndham and Swanson Sts, the top 1.5m of road surface continues to be removed to allow the installation of an extensive steel support structure ahead of the bulk excavation works for the City Rail Link (CRL) tunnels.

This structure will hold piled retaining walls apart during the CRL tunnel excavation along Albert St and will also support a pre-cast concrete deck that enables the entire excavation to be completed while maintaining a lane of traffic in each direction. 

In the coming months, the operation will progress towards Customs St and is expected to be completed in October. During this time, Connectus will also start excavating down to the level of the depth of the future CRL tunnels, progressively moving north from the Wyndham St end.

From 26 June, for about one year, southbound traffic will be diverted off Albert St to the Wyndham to Victoria St slip lane by the bluestone heritage wall. This provides the contractor a laydown and stockpiling area opposite the court house to facilitate the excavation and backfill operations associated with the tunnel construction.

Scheduled from 5 July, northbound traffic along Albert St will be temporarily diverted for three months via Swanson St West and Federal St to allow contractors more space to excavate the top 1.5m of roadway and install the large steel struts and pre-cast concrete traffic decks. Wolfe Street will be accessible from Federal Street but there will be no access from the Albert St end.

At the Albert/Customs intersection, construction is underway on the third of four sections of the traffic deck, which will form part of a bridge structure that spans the entire intersection, allowing all four traffic lanes to be re-established (likely by the end of September) while the CRL tunnels are constructed underneath.

Construction Albert and Customs Streets July 2017

Now that the replacement stormwater pipe has been installed, the shafts that received the tunnel boring machines are being sealed and backfilled. This will allow the hoardings and construction sites to be removed. The Swanson Street shaft has been completed and reinstated. The Wellesley Street shaft is expected to be completed and reinstated in August. The two shafts at Victoria Street will remain in place until October while strengthening of the Orakei Main Sewer is undertaken. This work is required before the start of construction on the future mid-town station.

^ back to top


27 June 2017

Karangahape Road inspections made

Construction work won't start in Karangahape Road before 2019 - but preparation has begun.

We never know what we will find under the streets once we do start digging. That's why we have to do some potholing and work out what utility lines are there. We survey each cable, pipe, and duct and then we can take that electronic information and start to model what that locality looks like. Then we can start to overlay other information like new structures such as the new Station walls, and see how these are currently interacting with the modelled utilities. If the utilities are in the way, then we can start assessing how and where we can relocate those affected utilities to.

Construction work won't start in Karangahape Road before 2019 - but preparation has begun.

We never know what we will find under the streets once we do start digging. That's why we have to do some potholing and work out what utility lines are there. We survey each cable, pipe, and duct and then we can take that electronic information and start to model what that locality looks like. Then we can start to overlay other information like new structures such as the new station walls, and see how these are currently interacting with the modelled utilities.

If the utilities are in the way, then we can start assessing how and where we can relocate those affected utilities to.

Here is an example below of what we found underground on this section of the corner of Albert and Customs Streets:

PUZZLE: This is a sketch by CRL team workers of what they found under that section of road

PUZZLE: This is a sketch by CRL team workers of what they found under that section of road


23 June 2017

View from the shaft

With the new stormwater pipe built to replace the pipe running up Albert St, here's what it looks like in the shaft on the corner of Victoria & Albert Streets.

A new reinforced concrete chamber is being built to connect the existing Victoria St stormwater line with the new pipe-jacked line you can see at the bottom right of the photo.


19 June 2017

The big red silos

It’s hard to miss the large red silos that have gone up in Lower Queen Street but they’re there to fulfill an important task in preparing Britomart Station’s Chief Post Office (CPO) building for CRL tunnel excavation.

Sodium Bentonite is an absorbent clay that expands when wet. In civil engineering applications bentonite is used as a mineral hydraulic barrier in diaphragm walls, foundations, tunnelling, horizontal directional drilling and pipe jacking.

Silos in Lower Queen Street

The silos are part of a specialised bentonite plant, shipped over from France by CRL contractor Downer Soletanche-Bachy Joint Venture, to help with the construction of diaphragm walls that will support the CPO building foundations and the CRL tunnel box. This week, three more silos will arrive to complete the set-up of the plant, which will remain on site until early 2018.

Sodium bentonite is an absorbent clay that expands when wet. At the CPO building, bentonite slurry (a mix of bentonite powder and water) will be pumped into the trenches being excavated for the diaphragm walls to ensure the sides don’t cave in and ground water levels remain constant. The slurry keeps surrounding earth stable until steel reinforced concrete can be added in its place.

Once concrete starts to be added from the bottom of the newly-created diaphragm wall, the bentonite is progressively displaced and sucked out of the diaphragm wall by a specialised hydraulic pump and transferred back to the silos. The slurry can then be re-used again and again as required.

When working around sensitive heritage buildings, this method has less impact than traditional piling techniques as it minimises noise, vibration and impact on natural ground water levels. 

^ back to top


12 June 2017

More work around the former CPO

This is the service trench which is being constructed on the Galway Street side of the station. This will house various services which connect to the new station.

HYDROFRAISE: This hydrofraise machine will be used to dig the wall panels which form the structural support for the tunnels. This machine will use the bentonite plant to dig down about 15 metres

HYDROFRAISE: This hydrofraise machine will be used to dig the wall panels which form the structural support for the tunnels. This machine will use the bentonite plant to dig down about 15 metres


8 June 2017

What's involved inside the CPO

This video from Downer NZ and Soletanche Bachy (DSBJV) shows the work they're doing at Britomart Transport Centre (the former CPO).


6 June 2017

Roadway removed for steel structure

At the southern end of Albert Street works, the top 1.5 metres of roadway is being removed. This allows for installation of an extensive steel structure to support both the pile walls and a pre-cast concrete deck so the excavation can be completed while maintaining a lane of traffic in each direction.

In the coming months, this operation will progress towards Customs Street and is expected to be complete in October.

During this time, our contractors Connectus, will also start excavating down to the level of the CRL, progressively moving north from the Wyndham Street end.

At the Albert/Customs Street intersection, construction is underway on the third portion of the traffic deck, which will form part of a bridge structure that spans the entire intersection, allowing all four traffic lanes to be re-established while the CRL tunnels are constructed underneath.

Now that the stormwater replacement has been completed, the shafts that received the tunnel boring machines will be sealed and back-filled. This will allow the hoardings and construction sites to be removed from Swanson and Wellesley Streets.

The two shafts in Victoria Street will remain in place until September while strengthening of the Orakei Main Sewer is undertaken. This work is required before the start of construction on the future mid-town station.

^ back to top


24 May 2017

Interior prepared for tunnels

At Britomart, work continues on preparing the interior of the Chief Post Office (CPO) for tunnel excavation.

The floor is being removed, piling works have started, the glass bridge that used to run between the CPO and Commerce Street is being removed, and diaphragm walls are being prepared ahead of tunnel excavation. In addition, a huge utilities trench has been dug in Galway Street.

With Lower Queen Street now closed to pedestrians, more substantial construction equipment will be installed and piling in the area will begin in October.

^ back to top


15 May 2017

Historic items uncovered

Interesting historical artefacts - such as these five vessels found behind the Chief Post Office building - continue to be found during CRL excavation works. Read more about it in our Hidden Treasures Found feature.


May 2017

New walkway unveiled

Lower Queen Street now has a new walkway linking Customs and Quay Streets. Its distinctive wave pattern reflects its harbourside location and lights up at night.  

The walkway is a joint effort between CRL, Precinct Properties and Activate Auckland. It's intended to provide a safe, well-lit and attractive route that separates pedestrians from CRL construction on the eastern side and the Commercial Bay property development on the western side. Vehicles have their own lane through Lower Queen Street to access Tyler and Galway Streets, either side of Britomart Station.

This walkway is expected to stay in its current location until August, when it will move further west and vehicles switch to the east to better manage truck movements for changing construction needs.

^ back to top