City Rail Link
images_banner_header_web.jpg

City Rail Link (CRL) images

IMAGES

 

For commentary about the latest construction developments see our

For more on the methods being used see our


Latest photos

DECEMBER 2017

NOVEMBER 2017

OCTOBER 2017

SEPTEMBER 2017

AUGUST 2017

JULY 2017

JUNE 2017

Construction contracts

SANDRINE

CONSTRUCTION CONTRACT 1

Britomart Temporary Station Entrance, & Lower Queen Street Tunnels

Construction Contract 1 involves:

  • Decommissioning and later restoring the former Central Post Office station building

  • Constructing a ‘temporary station facility’ to the rear of the CPO, constructing two rail tunnels under the CPO and through Lower Queen Street to the eastern ‘stub’ of the Commercial Bay site and from the western ‘stub’ of the Commercial Bay site to Customs Street. Construction Contract 1 commenced during July 2016 with construction of the temporary station concourse and accommodation facility. 

BRITOMART TRANSPORT CENTRE REINSTATEMENT

As part of CRL Construction Contract 1, the Britomart Transport Centre, situated within the former Central Post Office, was decommissioned to enable CRL tunnel portals to be constructed below. 

The current 'dead end' at Britomart will be superseded by east and west bound tunnels, completing the current rail network.

The CPO Building was designed by Claude Paton and government architect John Campbell and originally opened in 1912. 

As part of CRL works the CPO will be fully restored and reinstated to its former glory.

CITY RAIL LINK STATION DESIGNS

CONSTRUCTION CONTRACT 2

Pipe jack programme & Utility Diversions - Albert, Victoria, Swanson and Wellesley Streets

Construction Contract 2 included  pipe jacking a new stormwater main along the eastern side of Albert Street, between Swanson and Wellesley Streets and strengthening of the Orakei Sewer Main across Albert Street.

To enable the pipe jack and cut and cover tunnel works, the diversion or relocation of many essential utility services along Albert, Victoria, Swanson and Wellesley Streets was required.

This includes stormwater pipes, electricity supply cables, telecommunications cables, gas pipes, sewer pipes and any other service conduit that needs to be safely relocated. Utility diversion is a significant body of work which commenced during December 2015. Pipe jacking and cut & cover tunnel construction began during Quarter 4, 2016. 

The main body of work under Construction Contract 2 is the construction of twin cut and cover tunnels along Albert Street from Customs Street to Wyndham Street.

The tunnels will be constructed using the bottom-up construction method where a deep trench up to 18 metres deep is excavated and the tunnel constructed through it, then carefully back-filled and the surface reinstated. You can see more about the construction methods used

CRL GROUND BREAKING CEREMONY

On 2 June 2016,  Prime Minister John Key, Transport Minister Simon Bridges and Auckland Mayor Len Brown formally marked the historic start of the construction of the CRL at a ceremony at the Britomart Train Station.

These are the latest concept designs for the CRL stations.  There are two new stations - one mid-town (referred to as Aotea) and  Karangahape Road (referred to as Karangahape). There are also the latest images of Britomart post-CRL. You can read about the design concepts and stations

SIGNING OF THE
CRL LTD PARTNERSHIP AGREEMENT

The Finance and Transport Ministers and Auckland Mayor Phil Goff signed agreements to establish City Rail Link Limited to assume responsibility for delivering the CRL from 1 July 2017

DRONE PHOTOS