City Rail Link (CRL) milestones

Milestones

Read the CRL Business Case

CRL wins Sustainability Project of the Year

Albert Street piling works completed

An extra million on the trains in just three months

Strong International Interest in City Rail Link Construction

Sustainability rating awarded

Largest City Rail Link tender process starts

Expressions of Interest sought

Temporary entrance opened

One year on

Piling works starting on Albert Street

Signing of Heads of Agreement

Nine-storey piling giant comes to town

Historic start of construction of CRL

QEII Square pedestrian underpass closure

The Government brings forward funding for the CRL

Dawn blessing marks the start of work

CRL construction to be part of Precint development

Appeals to land designation resolved

Queen Elizabeth II Square road stopping

CRL Showcase launched

Construction consortia appointed

Digging set to start on City Rail Link

Crossing the Start Line

Change made to timing of CRL

CRL open days popular

Cost down, benefits up from City Rail Link design change

Design change leads to cost savings

CRL design work progressed

AT accepts commissioners’ recommendations

Commissioners recommend CRL designation

New hearing date confirmed

Downtown agreement next step on City Rail Link

Transport Minister writes to Mayor

Construction delay

Open Days popular

Submissions close

Land designated

Study into future transport

Information sessions for adjacent landowners held

Notice of Requirement lodged with Auckland Council

Route identified for CRL

Money approved to progress CRL

The City Centre Future Access Study

Transport Minister request further CRL Review

Auckland Council moves on CRL

Government agrees to review business case

Business case announced

Preliminary Business case

Finance Minister: Secure the route

 

 

 

 

The CRL is the largest single transport infrastructure project in New Zealand's history. It has been a vision for Auckland since the 1920s.

For those of us working on the CRL project over the last five years, it’s been a dream that has now become a reality through the power of conviction and hard work
— Chris Meale, CRL Project Director
IT'S ALL GO! AT Chair Lester Levy, Auckland Mayor Len Brown, Prime Minister John Key and Transport Minister Simon Bridges at the historic groundbreaking ceremony for the CRL in Downtown Auckland June 2016

IT'S ALL GO! AT Chair Lester Levy, Auckland Mayor Len Brown, Prime Minister John Key and Transport Minister Simon Bridges at the historic groundbreaking ceremony for the CRL in Downtown Auckland June 2016


Read the CRL Business Case

This 2015 document was Auckland Transport’s internal business case to facilitate the Gateway Review process prior to letting contracts for enabling works construction. It was not a joint business case with government.


Here are the big milestones:

Below you will find CRL project milestones going back to 2008.


First concrete poured

23 July 2017

The first two concrete base slabs for the CRL twin-tunnels have been laid on Lower Queen Street.

The 700mm-thick concrete slabs are the first eight metres of CRL tunnel box floor to be poured out of the total 3.45km length of tunnel to be constructed.

Located under the Lower Queen Street walkway, adjacent to the Zurich building, these tunnel stubs will eventually connect to sections of tunnel from Britomart Station and Albert Street.

CONCRETE: This is looking down the neighbouring Precinct Commercial Bay Fletcher Construction project where the first concrete slab base has appeared.  The foundations for the 39-level tower on the former site of the Downtown mall are being dug concurrently with the beginning of the CRL tunnels

CONCRETE: This is looking down the neighbouring Precinct Commercial Bay Fletcher Construction project where the first concrete slab base has appeared.  The foundations for the 39-level tower on the former site of the Downtown mall are being dug concurrently with the beginning of the CRL tunnels

The slabs are protected by a high-tech water-proofing system to keep saltwater out, as they’re sitting about 13 metres below sea level.

In about a week, construction will start on the walls for this short section of tunnel. When a roof is eventually placed over the top in few month’s time, the result will be the first completed section of tunnel box for the project. 

^ back to top


Bulk excavation work starts 

17 July 2017

Bulk excavation work has started for the cut and cover rail tunnels under Albert Street.

The excavation involves digging 18 metres (about five storeys) at the deepest (southern) point, using long-reach excavators above ground and smaller machinery inside the reinforced trench.

This represents about 10% of the 3.45km length of the twin-tunnel underground rail link,

The tunnels will then be constructed with a cast concrete floor, walls and roof before the trench is backfilled.

^ back to top


CRL Limited takes effect

01 July 2017

The government and council have established the company City Rail Link Limited (CRLL) to undertake the delivery of the project and this took effect today.

Yesterday afternoon, outside the Britomart Transport Centre, Finance Minister Steven Joyce and Transport Minister Simon Bridges signed the agreements with Auckland Mayor Phil Goff that establish City Rail Link Limited to assume responsibility for delivering the CRL, marking the next step in transforming Auckland’s public transport.

HISTORIC: At a ceremony to formalise the partnership, CRL Project Director Chris Meale, Auckland Deputy Mayor Bill Cashmore, Transport Minister Simon Bridges, Mayor Phil Goff and Finance Minister Steven Joyce

HISTORIC: At a ceremony to formalise the partnership, CRL Project Director Chris Meale, Auckland Deputy Mayor Bill Cashmore, Transport Minister Simon Bridges, Mayor Phil Goff and Finance Minister Steven Joyce

CRLL is a crown entity, listed under Schedule 4A of the Public Finance Act, jointly owned by the Crown and Auckland Council. The company has full governance, operational and financial responsibility for the CRL, with clear delivery targets and performance expectations.

Procurement responsibilities were transferred from Auckland Transport to CRLL.

The Crown and Auckland Council expect that the management, delivery and completion of the CRL will be an exemplar model for the efficient and effective provision of public infrastructure through central and local government collaboration.

NEW LOOK: Minister Joyce displays a CRL staff member's business card displaying the new CRL logo

NEW LOOK: Minister Joyce displays a CRL staff member's business card displaying the new CRL logo

Steven Joyce told the ceremony: “Today’s signing is the next milestone in this important addition to Auckland’s public transport system. Auckland’s population predicted to grow by more than 700,000 people over the next 30 years, the CRL will play an important role in getting people in and out of the city with ease."

“Once complete, the CRL will fundamentally change the way people get around central Auckland and demonstrates the Government’s is commitment to Auckland and its Public Transport systems."

“CRL is Auckland’s top new transport priority. It will double the capacity of the whole existing rail network and provide significant travel time savings for commuters,” Mr Bridges says.

“The Crown and Auckland Council have signed agreements transferring the project to CRLL, formalising their partnership to jointly fund and oversee it through to completion,” Mr Joyce says.

“Under the leadership of Sir Brian Roche as Chair, CRLL will drive delivery of this complex project.”

KiwiRail, the state-owned enterprise responsible for all rail operations, has a formal role in ensuring the CRL's interoperability with the wider rail network and the services, such as freight, that it provides.

MASSIVE: The official party at the signing inspect the large CRL  construction machinery outside Britomart

MASSIVE: The official party at the signing inspect the large CRL  construction machinery outside Britomart

AT and KiwiRail are engaged by CRLL to provide technical and operational support services.

It is governed by a board chairman and directors. 

Auckland Council and the Government appointed Mr Brian Roche as the establishment chair of City Rail Link (CRL) Limited.

Mr Roche is the Group Chief Executive of New Zealand Post Group, a position he will step down from in April 2017. He also chairs Antarctica NZ, Hurricanes GP Ltd, Major Events Investment Panel, Tait New Zealand Ltd and Wellington Gateway Partnership.

^ back to top


Stormwater pipe replacement completed

21 July 2017

The replacement stormwater pipe along Albert Street has been completed so the shafts that received the tunnel boring machines are being sealed and backfilled.

This will allow the hoardings and construction sites to be removed from Swanson and Wellesley Streets.

INSPECTION: Workers inspect the shaft at the end of the new stormwater shaft under Wellesley Street

INSPECTION: Workers inspect the shaft at the end of the new stormwater shaft under Wellesley Street

The Swanson Street shaft has been completed and reinstated. The two shafts at Victoria Street will remain in place until October while strengthening of the Orakei Main Sewer is undertaken. This work is required before the start of construction on the future mid-town station.

^ back to top


First tranche of City Rail Link funding

25 May 2017

Budget 2017 provides $436 million of new capital for Auckland’s City Rail Link (CRL), as the first tranche of the Government’s investment in this critical transport project for Auckland, Transport Minister Simon Bridges says.

“The Government announced in 2016 that it would support accelerating the delivery of the CRL to help address Auckland’s transport needs by committing to fund half of the expected $2.8 billion to $3.4 billion cost,” Mr Bridges says.

“The CRL is a game-changer for central Auckland and this funding demonstrates the Government’s commitment to Auckland and its public transport systems."

GAME-CHANGER: Minister of Transport Simon Bridges surveys a City Rail Link shaft

GAME-CHANGER: Minister of Transport Simon Bridges surveys a City Rail Link shaft

“CRL is Auckland’s top new transport priority. It will double the capacity of the existing rail network and cut travel time for commuters."

“The CRL is already bringing economic benefits to Auckland and New Zealand creating hundreds of jobs during construction,” Mr Bridges says.

^ back to top
 


CRL wins Sustainability Project of the Year

3 May 2017

The CRL project won Sustainability Project of the Year at the EY New Zealand Procurement Excellence Awards.

AWARD: CRL Project Director Chris Meale and Principal Sustainability Advisor Liz Root with the award

AWARD: CRL Project Director Chris Meale and Principal Sustainability Advisor Liz Root with the award

Judges said the CRL, New Zealand’s largest and most complex infrastructure project, “has been designed to the highest sustainability standards, standards unprecedented in New Zealand, with the design being recognised as ‘leading’ by the Infrastructure Sustainability Council of Australasia”.

Judges added: “The challenge to the team was to develop and embed these standards at the procurement stage across a project comprising eight different contracts. Taking learnings from the first contracting processes and expanding traditional notions of environmentally friendly outcomes to consider long-term social outcomes, we have no doubt that under the guidance of their procurement team with a focus on sustainability design, the CRL will be constructed and managed to the highest standards.”

The other finalists in the category were Air New Zealand and NZ Transport Agency.

^ back to top


Albert Street piling works completed

13 April 2017

The City Rail Link project has reached another milestone, with the last of 362 piles dug on Albert Street, between Customs Street and Wyndham Street.

‘Gomer’ - the nine-storey-high piling rig affectionately named after 1960s TV character Gomer Pyle - began piling in September last year. Each pile was drilled to a depth of 20 metres and filled with reinforced concrete, which will support the trench walls within which the CRL’s twin tunnels will be constructed.

Connectus, the project’s contractor, is now forming the concrete capping beams which will be placed on top of the piles to tie them together. Steel I beams will then span the width of the trench to brace the piles. This marks the start of construction of the ‘cut and cover’ tunnels across Customs Street and up Albert Street to Wyndham Street.

FINISHED: Gomer’s last pile on the corner of Albert and Customs Street

FINISHED: Gomer’s last pile on the corner of Albert and Customs Street

The cut and cover methodology is being used in this part of the project due to the geology, shallow position of the tunnel and proximity of underground utilities. It involves the excavation of a deep trench between the rows of piles and construction of the tunnel structure (essentially a concrete box), after which the trench will be backfilled and the road reinstated. This work is due to be completed in late 2018.

Last week, the tunnel boring machine (TBM) simultaneously excavating and installing a new stormwater main 18 metres under Albert Street, finished its 500-metre journey between Swanson and Wellesley Streets.

^ back to top


An extra million on the trains in just three months

6 April 2017

Auckland’s rail network is adding a million passenger trips every three to four months. Auckland Transport says another milestone has been reached with 19 million passenger trips for the year, an annual increase of 19.4%.

GETTING BUSY: Henderson Station

GETTING BUSY: Henderson Station

A million more trips were added in just 117 days - and such growth at around that rate has occurred for the past two years. This time in 2015 AT had just celebrated 13 million trips.

For the 12 months to March 2017 Auckland public transport patronage totalled just under 87 million passenger boardings, an increase of 6.9% on the previous year.

^ back to top


Strong International Interest in City Rail Link Construction

5 April 2017

The City Rail Link has attracted strong International interest in delivering the CRL tunnels and stations contract for Auckland.

Ten companies from Europe, China, Australia and New Zealand have participated in the pre-qualification phase of the contract and eight have been approved to move to the next phase which is Expression of Interest. The two that were not approved are specialist service providers best placed to provide sub-consultancy services to the eventual contractor.

Expressions of interest for the tunnel and station work will be released shortly, then evaluated and in about October two will be shortlisted for the tender phase.

^ back to top


Sustainability rating awarded

22 March 2017

Auckland’s City Rail Link project has been recognised for a “world first” - embedding cultural values into its sustainability approach.

The CRL was last night awarded a “Leading” Infrastructure Sustainability (IS) Design rating by the Infrastructure Sustainability Council of Australia (ISCA), the highest possible achievement in the IS scheme.

AWARD CEREMONY: Left to right Dale Burtenshaw, Project Director, Downer and Soletanche Bachy Joint Venture, Liz Root, CRL Principal Sustainability Advisor, CRL Project Director Chris Meale and Antony Sprigg, CEO ISCA

AWARD CEREMONY: Left to right Dale Burtenshaw, Project Director, Downer and Soletanche Bachy Joint Venture, Liz Root, CRL Principal Sustainability Advisor, CRL Project Director Chris Meale and Antony Sprigg, CEO ISCA

The rating is for the design and construction planning of Contract 1 – the work through and under Britomart Station and Lower Queen Street to the former Downtown Shopping Centre site. A Downer/Soletanche Bachy joint venture is the delivery partner for this contract. The designers are Aurecon, Mott MacDonald, Grimshaw, Jasmax and Arup.

This is only the second “Leading” rating awarded in New Zealand, the first also went to the CRL. It was for the design and construction planning (with Connectus) of Contract 2 – the Albert Street tunnels and a new stormwater main under Albert Street.

^ back to top


Largest City Rail Link tender process starts

2 February 2017

The largest component of the City Rail Link (CRL) project – the construction of the tunnels and new stations - took a major step forward today with the release of its first tender documents to the industry.

The project is picking up speed with Expressions of Interest sought only a fortnight ago for the design, procurement, installation and commissioning of all tunnel track work and rail systems between Britomart Station and the Western Line at Mt Eden.

There will be two new stations as part of the build of the underground rail line linking Britomart with the existing western line near Mt Eden. The new stations will be near Aotea Square with entrances at Wellesley and Victoria Streets and a station in Mercury Lane, just off Karangahape Road. The present Mount Eden train station will be extended and redeveloped.

Tender documents sent out today are for the tunnel and station works that involve:

  • Aotea Station: Cut and cover construction of a 15m-deep, 300m-long underground station and plant room box, including platforms, lifts and escalators to street level, plant rooms housing station and tunnel equipment, full station fit-out and entrances at either end at Victoria and Wellesley Streets
  • Karangahape Road Station: Mined construction of a 32m-deep underground station, including platform tubes and 150m-long platforms, lifts and inclined escalator to street level, plant rooms housing station and tunnel equipment within two shafts, full station fit-out, entrance at Mercury Lane and provision for a future entrance at Beresford Square
  • Tunnels: Twin-bored tunnel construction (circa 7m diameter) between the Mt Eden station and the southern end of Aotea Station
  • The provision of maintenance services for the new stations.

^ back to top


Expressions of Interest sought

19 January 2017

Expressions of Interest are being sought for the design, procurement, installation and commissioning of all tunnel track work and rail systems between Britomart Station and the Western Line at Mt Eden. The work involves the provisioning of track slab, track, overhead line, signalling, control systems, tunnel ventilation, fire strategy and communications system.

The successful contractor will be responsible for the integration of the systems with the existing operations at Britomart and Mt Eden and the new tunnels and stations being built for the CRL. The documents, the first to be released to build the project past its current Britomart and Albert street sites, have been prepared as a result of the agreement between the Government and Auckland Council to jointly fund the project.

The C7 systems package will be procured using an Early Contractor Involvement (ECI) model followed by a Design and Construct contract.

^ back to top


Temporary entrance opened

17 January 2017

TEMPORARY:  A temporary Britomart entrance was built with entrances at Commerce, Galway and Tyler Streets

TEMPORARY:  A temporary Britomart entrance was built with entrances at Commerce, Galway and Tyler Streets

The Chief Post Office building  (the Britomart Transport hub) was closed for strengthening works before work starts on the City Rail Link (CRL) tunnels. The temporary entrance will be in use for three years.

^ back to top


One year on

12 December 2016

CRL project Director Chris Meale reported on CRL construction one year on.

Construction on the underground rail line linking Britomart and the city centre to the western line near Mt Eden began 12 months ago.

FIRST YEAR: CRL project Director Chris Meale checking out construction progress

FIRST YEAR: CRL project Director Chris Meale checking out construction progress

More than 90,000 people work in the city centre daily. Auckland Transport data over the past 12 months shows:

  • More people are travelling into the city. The morning peak in September was 1.6 per cent higher than a year previously
  • Fewer people are bringing in their car. In September 2015, 54 per cent of peak morning visitors were in a private car. This year the number has fallen to 49 per cent
  • More Aucklanders are using public transport and cycling. Train patronage in October was 17.7 per cent higher than the previous October
  • Mean peak traffic speeds in the city centre are the same or slightly higher than before CRL began.

Chris Meale said impressive statistics are being achieved for New Zealand’s biggest infrastructure project.

PROGRESS: Transport minister Simon Bridges and then Auckland Mayor Len Brown inspect CRL construction at the Victoria Street shaft

PROGRESS: Transport minister Simon Bridges and then Auckland Mayor Len Brown inspect CRL construction at the Victoria Street shaft

So far:

  • All contractors have completed a combined total of 273,000 hours of work. This equates to one person working 136 years
  • The Connectus Joint Venture (McConnell Dowell and Hawkins) is constructing the cut and cover tunnels under and along Albert St from Customs St to Wyndham St. CRL works from Britomart Station to Wyndham St are on schedule. All four shafts required to move deep stormwater pipes in Albert Street have been excavated to the required depth. Tunnelling is underway and has advanced 60m from Victoria Street to Swanson Street with the contractor advancing four to six pipes a day. At this rate, the 300m drive to Swanson Street will be completed by Christmas
  • The contract requires 360 piles to be constructed and 125 jet grout columns. So far 100 piles and 100 jet grout columns have been constructed. This is ahead of schedule despite being carried out in areas of the most unknown geotechnical condition
  • Downer NZ and Soletanche Bachy Joint Venture who are building a temporary entrance from Commerce Street for the Britomart Transport Centre are on target to open the building by 16 January next year when the Queen Street entrances close
  • AT contractors have achieved full environmental compliance at every audit. Two isolated incidents of uncontrolled run off were dealt with quickly
  • One contractor has achieved a leading rating for sustainability which is above the target of excellent. A rating for the other contractor is pending
  • There has been only one medical injury.

^ back to top


Piling work starting on Albert Street

11 November 2016

Gomer, the 9-storey-high piling rig (affectionately named after comical 1960s TV character, Gomer Pyle), has made good progress at the Albert and Customs Street intersection and is now starting his way up Albert Street.

Due to the busy central city location of the works, the worksite is complex. Gomer’s 11m x 5.5m footprint means he takes up most of the width of the road when he turns around! With Fletcher Building’s demolition of the old Downtown Shopping Centre, Custom Street’s capacity has been squeezed for buses and all other traffic.

However, Gomer has already dug more than 17 piles of up to 20 metres in depth, which have been filled with reinforcing cages and concrete, and he will have completed 362 piles in total when he reaches his final destination, 20m past Wynyard Street.

Gomer’s good progress means we are on track to start digging the 350-metre cut and cover tunnels up Albert Street in the first quarter of 2017.

^ back to top


Signing of Heads of Agreement

14 September 2016

An historic milestone was reached today with Mayor Len Brown signing an agreement with Transport Minister Simon Bridges on funding for the City Rail Link. 

HEADS OF AGREEMENT: Auckland Mayor Len Brown and Transport Minister Simon Bridges talk to media

HEADS OF AGREEMENT: Auckland Mayor Len Brown and Transport Minister Simon Bridges talk to media

This will allow the "main works” tendering process to begin and for specialist constructors to make available the people and machinery needed to build the CRL.

Watch the signing:

Features include:

  • A 50/50 funding arrangement where Auckland Council and the Crown each pay half of the total capitalised costs of the project
  • The principals to the agreement, referred to as “sponsors”, are the Government and Auckland Council
  • The establishment of a company (City Rail Link Limited) through which the Government and Council will oversee the delivery of the project
  • Joint share in development opportunities arising from the project
  • The technical and operational aspects of project delivery are to be carried out by Auckland Transport working to the City Rail Link company
  • KiwiRail have a formal role in ensuring the CRL’s interoperability with the wider rail network and the services it provides, such as freight.

Today’s signing took place at the Victoria St underground shaft from where tunnel boring machines will start the work. 

^ back to top


Nine-storey piling giant comes to town

5 September 2016

One of the world’s biggest piling machines has landed in Auckland and will be moved in to position in lower Albert St this month.

The Soilmec SR 100 has been shipped to NZ from Italy and will be used to drill tunnel piles to about 20 metres deep, starting mid October.

When fully unfurled with attachments, the Soilmec SR 100 will be 5.5m wide and 11 metres long. The mast is about 29 metres high (9 storeys high).

^ back to top


Historic start of construction of CRL

2 June 2016

The Prime Minister John Key, Transport Minister Simon Bridges and Auckland Mayor Len Brown formally marked the historic start of the construction of the CRL at a ceremony at the Britomart Train Station.

GROUNDBREAKING: Balloons and an explosion helped mark the start of construction

GROUNDBREAKING: Balloons and an explosion helped mark the start of construction

Watch the CRL groundbreaking ceremony and speeches

POPULAR: Aucklanders grabbed every advantage point they could outside Britomart to witness the important day

POPULAR: Aucklanders grabbed every advantage point they could outside Britomart to witness the important day

The first contract documents for the entire City Rail Link (CRL) project from the city to Mt Eden also went out to the industry, marking another important milestone for the project.

AUCKLAND'S FUTURE: Young performers symbolised the generations that will benefit most from the CRL

AUCKLAND'S FUTURE: Young performers symbolised the generations that will benefit most from the CRL


QEII Square pedestrian underpass closure

29 March 2016

From today, the pedestrian underpass between Britomart Station and Queen Elizabeth II Square will be closed.

We are closing the underpass to prepare for the CRL early works.

^ back to top

CLOSING:  The underpass to Britomart platforms

CLOSING:  The underpass to Britomart platforms


The Government brings forward funding for the CRL

27 January 2016

The Government announced it will work with Auckland Council to bring forward the start date of the City Rail Link. The Government would also work to formalise its funding commitment from 2020, which the Council has indicated would allow construction of the main works to start in 2018, at least two years sooner than currently envisaged.

It said the decision had been driven by strong growth in rail patronage and the need to provide investment capacity for large-scale developments in the CBD.

EXCELLENT NEWS: Minister of Transport , Simon Bridges and Mayor Len Brown

EXCELLENT NEWS: Minister of Transport , Simon Bridges and Mayor Len Brown

Mayor Len Brown, calling it excellent news, said: "I have long championed the City Rail Link project because it will be transformational not only to keep Auckland moving but also to boost the city's economic and social life. Its benefits will be felt across Auckland as well as building a great heart in the central city."

^ back to top


Dawn blessing marks start of work

21 December 2015

Preliminary work for the City Rail Link began with a dawn blessing of the work site.

BLESSING: About 80 people gathered on the corner of Victoria and Albert Streets in the central city as kaumatua blessed the worksite between Swanson and Wellesley Streets where the first part of the project had begun.

BLESSING: About 80 people gathered on the corner of Victoria and Albert Streets in the central city as kaumatua blessed the worksite between Swanson and Wellesley Streets where the first part of the project had begun.


CRL construction to be part of Precinct development

11 December 2015

A joint announcement by Auckland Council and property company Precinct announced that the first stage of the City Rail Link project would be built on the site of the Downtown Mall, between lower Queen Street and Albert Street. The construction will take place as part of the 'Commercial Bay' development by Precinct.

The 39-storey, $681 million Commercial Bay development is one of several major new developments that will come to the city centre in the next few years.

PRECINCT: Fletcher Construction will construct a portion of CRL tunnels through the Commercial Bay construction site. Commercial Bay will be developed by Precinct Properties Limited on the site of the former Downtown Shopping Centre.

PRECINCT: Fletcher Construction will construct a portion of CRL tunnels through the Commercial Bay construction site. Commercial Bay will be developed by Precinct Properties Limited on the site of the former Downtown Shopping Centre.


Appeals to land designation resolved

27 August 2015

The City Rail Link reached a major milestone with all appeals to its land designation having been resolved by agreement or dismissal. Five of the six appeals were settled and the only appeal that went to the Environmental Court has been dismissed.

^ back to top


Queen Elizabeth II Square road stopping

17 June 2015

AT proposes stopping Queen Elizabeth II Square as a legal road so that the Downtown Shopping Centre block can be redeveloped and construction can begin on the underground tunnels for the City Rail Link. 

Depending on confirmation of the road stopping and an associated rezoning process, the land forming the existing square will be sold and combined with the Downtown Shopping Centre site. As part of the redevelopment arrangements, Auckland Council will secure a new east - west public pedestrian link across the area to connect lower Queen Street and Lower Albert Street. There will also be a north - south laneway through the Downtown Shopping Centre block (referencing the former Little Queen Street).

The proceeds from the sale of the square will be reinvested in alternative public spaces along the downtown waterfront. 

Before the sale can begin, the road status of the square needs to uplifted, a legal public process AT is responsible for as the regulatory authority.

Key points

  • AC has agreed to sell Queen Elizabeth II Square in a deal that provides better east-west and north-south pedestrian links in the area, sees the property owner building the CRL tunnels below its site as an integral part of the development and frees up funding for the improvement of other nearby public spaces
  • AT is the regulatory authority responsible for the legal process, known as road stopping, required to remove Queen Elizabeth II Square’s status as a road so it can be sold
  • Road stopping is a public process and is publicly notified. People have 40 days to make a submission to AT by Tuesday 28 July
  • An independent commissioner will consider and hear submissions on the road stopping process and make a recommendation to AT. AT’s decision can be appealed to the Environment Court.

If you object to this proposal, you can lodge an objection in writing to Deborah Godinet, Group Manager Property and Planning, Auckland Transport, Private Bag 92250, Auckland 1142 before 4pm, Tuesday 28 July 2015.

^ back to top


CRL Showcase launched

15 May 2015

Aucklanders will have the opportunity to learn more about the City Rail Link when AT brings its CRL Showcase to town centres in west, east, south and north Auckland later this month.

POPULAR:  An earlier showcase found Aucklanders were keen to learn about CRL

POPULAR:  An earlier showcase found Aucklanders were keen to learn about CRL

The showcase is coming town centres in response to requests from many of those who attended the showcase in the City Centre in April, for it to be taken to smaller centres.

^ back to top


Construction consortia appointed

25 February 2015

The appointment of two construction consortia to commence the first phase of the CRL construction in the Downtown area was announced.

Auckland Transport appointed two Joint Venture contractors for the work: Downer NZ and Soletanche Bachy JV and Connectus (McConnell Dowell and Hawkins JV) for the first phase of the design at a cost of about $3 million. The next phase will provide for a negotiated contract to construct the City Rail Link.

The Downer-led joint venture would progress the CRL work through and under Britomart Station and Queen Street to the Downtown Shopping Centre site. The contract includes establishing temporary accommodation for Britomart Station's ticketing and customer service operations, underpinning the historic former Chief Post Office building, to allow the construction of rail tunnels beneath and reinstating Britomart Station and upgrading urban space and surrounding spaces.

The Connectus Consortium would construct the cut and cover tunnels under and along Albert Street from Customs Street to Wyndham Street. The work would start with the relocation of a major storm water line in Albert Street between Swanson and Wellesley Streets.

^ back to top


Digging set to start on City Rail Link

5 February 2015

Major roads in central Auckland will be dug up before the end of the year to make way for the CRL.

Resource consents for the first section of the rail tunnel were publicly notified today.

^ back to top


Crossing the Start Line

22 December 2014

Bright red lines have been painted on streets in Downtown Auckland and in QEII Square to mark the centre of each of the two tunnels to be built late next year in preparation for the CRL.

Aucklanders using public transport in the area will now be able to see exactly where the CRL tunnels will be, and areas which will be affected by construction works.

^ back to top


Change made to timing of CRL

9 December 2014

Auckland Council's Governing Body agreed to push out the timing for the start of the City Rail Link in its 10-year budget to 2019/19.

The council did have the CRL project commencing from 2015/16, based on an assumption government's funding contribution for the project would also start next year, five years earlier than the government had indicated.

DECISION TIME: Auckland Council's Governing Body

DECISION TIME: Auckland Council's Governing Body

The decision to amend the timing, which was agreed 14 votes to 6, came in response to discussions held with Audit NZ on the council's draft budget.

The council would still invest as planned $280 million to do enablement works in the first three years of the plan (2015-18) as well as spend $120 million for ongoing land acquisition. But construction is now scheduled to start three years later in 2018/19, assuming the government had agreed to start its funding at that stage. The CRL was now expected to be completed in 2023.

^ back to top


CRL open days popular

2 September 2014

About 200 people attended three City Rail Link open days in the past week at the Pitt Street Methodist Church, the Mahatma Gandhi Centre in Eden Terrace and the Town Hall.

The open days provided information on the decision to replace Newton station with a redeveloped Mt Eden Station, an update on the Notice of Requirement process and introduced the regional consents process.

OPEN DAY: CRL project team members answer questions

OPEN DAY: CRL project team members answer questions

Using iPads, visitors were able to view the stations in three dimensions and see how they will fit into the surrounding landscape.

Common areas of interest were the station designs, the running plans for the trains once the CRL is complete and core samples from boreholes drilled along the route.

^ back to top


Cost down, benefits up from City Rail Link design change

1 August 2014

Auckland Transport (AT) has decided to redevelop the existing Mt Eden Station and connect it to the CRL rather than build a new underground station at Newton.

Since the CRL’s concept design was developed two years ago, there has been concerted effort to optimise the design and drive value for money. The on-going design improvement process included a comprehensive review of all project elements by an international “challenge team” of experts.

The improved design will connect passengers at Mt Eden Station to the CRL which previously bypassed them and improve operational reliability through the provision of a separated east-west junction so train lines won’t need to cross over each other.

PLAN: This is an indicative rail plan based on the new station layout

PLAN: This is an indicative rail plan based on the new station layout

Benefits

Customer Experience

  • Improves reliability with grade separated junction
  • Allows Mt Eden passengers to connect to CRL
  • Saves time for 3000 passengers a day - 95 a day have longer journeys
  • Deep lifts replaced by open to air platforms
  • Provides better modal transfer

Development

  • Leverages development of construction site
  • Better fit with wider development potential

Construction impacts

  • Reduces construction disruption on Symonds St by 12-18 months
  • Reduces construction effects on some properties
  • Six fewer surface properties required
  • About a dozen fewer sub-surface properties required

Cost

  • Reduces capital cost by $124 million
  • Reduces operational expenditure.

^ back to top


Design change leads to cost savings

31 July 2014

Auckland Transport announced a significant design change to the City Rail Link which would save over $150 million, improve the reliability and journey time of train services, minimise construction disruption in Symonds Street and reduce property purchase requirements.

AT decided to redevelop the existing Mount Eden station and connect it to the City Rail Link rather than build a new underground station at Newton. AT chairman Lester Levy said the change would reduce cost by removing the very deep Newton station, which would also reduce construction disruption in upper Symonds Street by 12 to 18 months.

^ back to top


CRL design work progressed

10 July 2014

Auckland Transport is seeking Registrations of Interest for the final phase of design for the Britomart end of the City Rail Link (CRL). 

  • AT is engaging with the construction industry to finalise design on a discrete section of the CRL that most affects other proposed inner city development
  • AT wants to enable other development in the city to proceed by having design advanced for the CRL enabling works when finance becomes available
  • Finalising the design will also allow AT to establish management plans and seek the consents necessary for enabling works in advance of the works
  • Engaging early with the industry will ensure a collaborative, cost effective design that has been tested for staging of constructability
  • The CRL has not yet received a mandate from council to start construction and the final design will be taken forward only when this has occurred.

The contract includes Design Development and Consenting for the area between Britomart Station and Wyndham Street. 

Registrations of Interest close on the 6th of August.

Design of the Britomart end of the City Rail Link was being progressed with Auckland Transport asking the construction industry to register its interest in the work. AT said the focus of the design would be on the downtown section of the City Rail Link, from Britomart through Queen, Customs and Albert Streets to Wyndham Street.

^ back to top


AT accepts commissioners' recommendations

14 April 2014

Auckland Transport accepted the recommendation by planning commissioners to confirm the land requirements for the CRL.

Auckland Transport's chief executive David Warburton said: "It's a big step forward for Auckland. A proposal to extend rail through the city centre has been on the books in some form or other for almost a hundred years but never got beyond an idea. At least we have a designated route."

^ back to top


Commissioners recommend CRL designation

5 March 2014

Independent planning commissioners announced unanimous recommendation that the land required to build, operate and maintain the City Rail Link be set aside for the project. The five commissioners, who heard AT's planning application for the CRL recommended that the designation for the land be confirmed, subject to conditions that address issues raised by submitters.

Mayor Len Brown noted the commissioners' agreement with business leaders, such as the Auckland Chamber of Commerce, that the transport and wider benefits of the project were largely undisputed. The Mayor said he was particularly encouraged by the commissioners' satisfaction that alternative sites, routes and construction methodologies for the project had been adequately considered.

^ back to top


New hearing date confirmed

24 October 2013

The hearing of notices of requirement to designate land to build, operate and maintain the City Rail Link has been adjourned until 10 - 11 November. The commissioners have adjourned to consider the material provided in the application.

^ back to top


Downtown agreement next step on City Rail Link

8 July 2013

Auckland Council agreed to negotiate with Precinct Properties to coordinate timing of future development plans for its Downtown shopping centre with the construction of the part of the City Rail Link that needs to pass below the complex.

^ back to top


Transport Minister writes to Mayor

July 2013

Transport Minister Gerry Brownlee wrote to Auckland Mayor Len Brown, confirming that “government has committed to a joint business case for the City Rail Link with Auckland Council in 2017, and to providing its share of funding for a construction start in 2020.”

The letter also raised matters relating to future governance, determining of funding shares and circumstances that could trigger an earlier business case:

  • Auckland city centre employment increases by 25% over current levels
  • Annual rail patronage is on track to hit 20 million trips well before 2020.

^ back to top


Construction delay

26 June 2013

Prime Minister John Key confirmed that the Government would back a city rail link in Auckland but delay the construction by five years. The Government wasn't ruling out funding coming from the future investment fund, which uses the proceeds from the partial sale of state-owned assets.

^ back to top


Open days popular

15 April 2013

Auckland Transport began holding three open days for anyone who would like to find out about the City Rail Link and to talk to the project staff.

FLYER: Throughout the project, City Rail Link's open days have been popular with the public and those curious about the project

FLYER: Throughout the project, City Rail Link's open days have been popular with the public and those curious about the project


Submissions close

20 March 2013

An application to designate land to build and operate the City Rail Link was open for public submission until 19 March 2013. Submissions have now closed.

Hearings are anticipated in the third quarter of 2013.

^ back to top


Land designated

24 January 2013

Auckland Transport announced that an application to designate land to build and operate the CRL was open for public comment. Auckland Transport has served Notices of Requirement on Auckland Council to hand the land, required to build and operate the CRL, identified in the District Plan.

^ back to top


Study into future transport

13 December 2012

A study into the future transport needs of Auckland was released revealing a looming crisis as the city's population growth exceeds the ability of the transport network to cope. The City Centre Future Access Study (CCFAS) was commissioned by Auckland Transport and warned of significant delays and congestion on all routes into the city within the next 10 years.

The CCFAS identified the City Rail Link as essential. It says that bus-only investment will provide for short-term benefits but in some cases will be 'worse than doing nothing' for private vehicle travel times.

STUDY: City Centre Future Access Study warned that the Auckland City Centre "will face significant access issues across all entry points from as early as 2021."

STUDY: City Centre Future Access Study warned that the Auckland City Centre "will face significant access issues across all entry points from as early as 2021."

Transport Minister Gerry Brownlee said the study was "a useful addition to the debate on long-term transport management in central Auckland" but "fell some way short of convincing the Government it should provide financial support to any fast tracking of the proposed City Rail Link."

^ back to top


Information sessions for adjacent landowners held

15 - 20 September 2012

Prior to public notification, Auckland Transport held three information sessions for immediately adjacent land owners regarding potential CRL effects and how these will be managed.

^ back to top


Notice of Requirement lodged with Auckland Council

10 September 2012

Auckland Transport (AT) has identified a land footprint for the City Rail Link (CRL) and after talking to directly affected landowners and advising them on the project, Auckland Transport has initiated a formal planning process with a notice of requirement being lodged with Auckland Council.

^ back to top


Route identified for CRL

3 July 2012

Auckland Transport announced it had identified a route through the city centre for the City Rail Link and was making contact with directly affected landowners prior to seeking planning protection for the route.


Money approved to progress CRL

13 March 2012

Auckland Council's Strategy and Finance committee brought forward money from the 2012-2013 City Rail Link budget to the current financial year in order to continue progress protecting the eventual route.

$6.3 million was to be spent on work including geotechnical surveys, utility and building assessments, contaminated site reports and rail operations modelling. $1.7 million would  go towards meeting the government's requirement that additional work be undertaken on CBD growth projections and access issues.

^ back to top


The City Centre Future Access Study

February 2012

The City Centre Future Access Study was the agreed process across Auckland and government agencies to:

“Develop a robust and achievable multi-modal programme for transport into the Auckland City Centre, which considers a thorough analysis of alternatives and identifies the optimal mix of modes to meet demand. This should include consideration of the prioritisation and sequencing of projects”.

In February 2012, new Minister of Transport, Hon Gerry Brownlee, confirmed his comfort with the scope of the study and appreciated the close engagement of government officials whilst expressing some reservations as to the time-line.

The study reported in December 2012. It established that the CRL was the optimal “headline” project, and that additional surface bus improvements were required.

CCFAS was effectively an indicative business case in terms of the Better Business Case stages. Whilst it included economic appraisal, the BCRs were relative not absolutes.

^ back to top


Transport Minister requests further CRL Review

20 July 2011

The Mayor of Auckland, Len Brown, received a letter from the Minister of Transport, the Hon Steven Joyce, which requested a further CRL Review [to] include:

  • “finalisation of the spatial plan and master plan including establishing achievable growth projections for the CBD
  • demonstration of commitment to resolving current CBD access issues, for example by improving bus operations and addressing capacity issues
  • evidence of rail patronage increases, particularly in the morning peak, residential intensification and CBD regeneration as a result of current investment
  • beginning implementation of large scale residential developments along the rail corridors
  • implementation of additional park and ride sites, and changes to bus feeder services."
TRANSPORT MINISTER: Requests more information

TRANSPORT MINISTER: Requests more information

A project team was formally established to progress the CRL on 1 November 2011. As set out above Phase 1 of the Programme includes progressing:

1.     The designation process

2.     Responding to the Minister’s Letter

^ back to top


Auckland Council moves on CRL

28 June 2011

The Governing Body of Auckland Council resolved:

  • That the Council directs Auckland Transport to seek a designation for the City Rail Link
  • That the Council confirms Auckland Transport’s financial responsibility for the Project, subject to Council funding being approved and available for any local share of the Project
  • That the Council and Auckland Transport will prepare draft agreed terms for a Heads of Agreement between Auckland Council and Auckland Transport, which sets out the basis upon which Auckland Transport will have financial responsibility for the Project.

^ back to top


Government agrees to review business case

21 December 2010

Transport Minister Steven Joyce asked officials from the Ministry of Transport, the Treasury and the NZ Transport Agency to work with Auckland Transport, Auckland Council and other agencies to review the business case for a City Rail Link (CRL).

^ back to top


Business case announced

24 November 2010

Auckland Mayor Len Brown released a business case for an underground rail link that highlighted major economic and transport benefits for Auckland.

CRL PUSHED: Auckland Mayor Len Brown promoted the buisness case as compelling and said “The potential urban redevelopment and additional growth derived from investment in this infrastructure would make the project transformational not just for Auckland, but for New Zealand as a whole.”

CRL PUSHED: Auckland Mayor Len Brown promoted the buisness case as compelling and said “The potential urban redevelopment and additional growth derived from investment in this infrastructure would make the project transformational not just for Auckland, but for New Zealand as a whole.”

The independently prepared business case investigates the economic viability of a tunnel that would improve rail links into the city. It would include three stations at key locations to ensure most of the central business district is no further than 500 metres from any CBD station.

BUSINESS CASE:  The CRL Business Case has pointed out the economic benefits to Auckland (Graph: AT's internal business case 2015)

BUSINESS CASE:  The CRL Business Case has pointed out the economic benefits to Auckland (Graph: AT's internal business case 2015)

A variety of choices were considered as part of the business case, including improving bus capacity, an expanded Britomart rail station, and a central city bus tunnel with three stations. The report ranks the rail link highest for cost effectiveness and impact because of the way it would unlock unused capacity across the whole rail network.

The Minister of Transport asked the Ministry of Transport, (MoT) and Treasury, in conjunction with the New Zealand Transport Agency (Transport Agency), to review the Initial Business Case (the Review). 

The purpose of the Review was to formally assess the Initial Business Case and provide advice on the merits of the CRL as a transport and economic investment, and when the project might be required. The Review was also intended to assist in determining if, how and when to progress with the CRL. Management from AT and Council participated in the analysis undertaken for the Review, supported by APB&B and other advisors.

That Review was undertaken from December 2010 through to May 2011 with the report released on 31 May 2011. In the Review the MoT concluded that “there was a strategic case for lodging a notice of requirement and it would make good sense to proceed with it”.

At the same time AT, Council and their advisers undertook a review of the economic evaluation of the project, concluding that “taking into account the wider transport policy initiatives which are planned, the City Rail Link would deliver overall benefits exceeding overall costs, with the benefit cost ratio ranging from 1.1 to 2.3.” (Auckland City Rail Link Updated Economic Evaluation 20 May 2011, Auckland Transport/Auckland Council May 2011).

^ back to top


Preliminary business case

2009

The Auckland Regional Transport Authority (ARTA) and KiwiRail (KRG) (previously ONTRACK) commenced an investigation to designate a route for the City Rail Link (CRL) for inclusion in Auckland’s District Plan. 

A consortium of AECOM, Parsons Brinckerhoff and Beca (APB&B) was appointed by KRG and ARTA to identify the preferred route, prepare the concept design for the preferred option together with a business case to support the Notice of Requirement (NOR), and prepare the NOR documentation. A preferred option for the route was identified in early 2010 and approved by ARTA and KRG. This preferred option was endorsed by the Auckland Regional Council, Auckland City Council, and the Auckland Regional Transport Committee.

In November 2010, AT, Council and KRG released the findings of this work (the Initial Business Case) and forwarded these findings to the Government for its consideration.

^ back to top


Finance Minister: Secure the route

2008

Auckland City Council representatives drew to the Government’s notice the intended redevelopment of the Downtown Shopping Centre that would preclude the extension of the metro rail from its terminus at Britomart to the North Auckland Line as was contemplated in Auckland’s formal transport planning documents such as the Regional Land Transport Strategy.

In response, the then Minister of Finance, Hon Dr Michael Cullen, wrote to the Chair of the New Zealand Railways Corporation stating that it “was in the long term public interest to secure and protect the CBD tunnel route even though construction may not take place for many years” and advising that it was “appropriate for ONTRACK to assist in the protection of the CBD tunnel route by acting to protect the route at the earliest appropriate opportunity.”

^ back to top