City Rail Link
Procurement_Auckland-City-iStock_000045029892_web.jpg

Procurement

Procurement 

 

City Rail Link is committed to a robust and transparent procurement process focused on risk management, value and ensuring a fair and equitable outcome.


Latest procurement news

  • The C6 Mt Eden Stormwater Main Relocation RFT closed on 3 August 2017
  • The C3 Stations and Tunnels EOI tender closed on 19 July 2017
  • The C3 Stations and Tunnels EOI was released to invited respondents in May 2017
  • The C6 Mt Eden Stormwater Main Relocation RFT was released to interested organisations in May 2017
  • 3 respondents are shortlisted to proceed to the C7 Systems, Integration, Testing and Commissioning RFT phase.

Find out more about


Procurement packaging and timeline

The CRL will be delivered in five principal packages

The geographic location of the work packages is shown on this map below


Procurement Timeline

The timeline for procurement of work packages is listed below. This table lists the dates a tender was released or is intended to be released. It will be updated as dates are achieved and confirmed.

table for procurement page.jpg

Procurement Package Progress

C3 Stations and Tunnels

The C3 Stations and Tunnels pre-qualification phase is complete. Ten submissions were received and eight respondents pre-qualified and have been invited to proceed to the EOI phase. The eight respondents are:

  • Acciona Infrastructure New Zealand Limited
  • Bam International Australia Pty Limited
  • China Machinery Engineering Corporation (CMEC) JV
  • CPB Contractors Pty Limited
  • Ferrovial Agroman (New Zealand) Limited
  • Salini Impregilo S.p.A
  • The Fletcher Construction Company Limited
  • Vinci Construction Grands Projets S.A.S (VCGP) JV

^ back to top


C5 Western Line

The final contract model for the C5 work package is currently being determined. The current preference is for a collaborative procurement model.  


C6 Mt Eden Stormwater Main Relocation

The C6 Mt Eden Stormwater Main Relocation RFT was released in May 2017.


C7 Systems, Integration, Testing and Commissioning

The C7 Systems, Integration, Testing and Commissioning EOI evaluation is complete. Eight submissions were received and three respondents have been shortlisted to proceed to the RFT phase. The shortlisted respondents are:

  • John Holland (NZ) Ltd
  • Laing O’Rourke Australia Company Pty Ltd
  • RCR (Infrastructure) NZ Ltd

C8 – Wider Network Improvements

The final contract model for the C8 work package is yet to be determined including whether some of the projects are included in the C5 or C7 scope of works.


 C9 – Britomart East

This work package is not currently being progressed for procurement as the timing of the works is post CRL opening.

^ back to top


Industry Briefing

The CRL Industry Briefing was held on 29 November 2016. The briefing was well attended and focused on the procurement process, governance and technical aspects of the project. An information booklet was provided on the day to all attendees. See links below to the presentation slides and information booklets.

Read here or download the presentation material

CRL Industry Briefing Presentation (PDF 4MB - 30 pages)


Industry Briefing information booklet - section 1 and 2
(PDF 4MB - 32 pages)


CRL Industry Briefing Technical Presentation (PDF 6MB - 83 pages)


Industry Briefing information booklet - section 3 (PDF 14MB - 28 pages)


Work Package descriptions

C3 Stations and Tunnels

C3 will be procured using a design and construct model with a lump sum price based on a bespoke contract. A portion of the bid costs for any unsuccessful short-listed C3 bidder will be paid in return for any intellectual property rights and effort expended.

Aotea Station - Cut and cover construction of a 15m-deep, 300m long underground station and plant room box, including platforms, lifts and escalators to street level, plant rooms housing station and tunnel equipment, full station fit-out and entrances at either end at Victoria and Wellesley Streets.

Karangahape Station - Mined construction of a 32m-deep underground station, including platform tubes and 150m-long platforms, lifts and inclined escalators to street level, plant rooms housing station and tunnel equipment within two shafts, full station fit-out, entrance at Mercury Lane and provision for future entrance at Beresford Square.

Tunnels - Twin-bored tunnel construction (circa 7m diameter), assuming a launch chamber at Mt Eden and reception chamber at the southern end of Aotea Station.

Newton junction to Western Line - A grade-separated junction between the east and west facing connections, with mined caverns for the turnouts, and cut and cover tunnels. Construction of a new platform for the CRL line in a 7m-deep open trench linked via escalator, stairs and lifts to the Mt Eden station platform on the Western Line, grade separated junctions, construction of a station group control centre above the station entrance and associated MEP and fit-out.

Asset Management - The provision of maintenance services for the three new stations.

^ back to top


C5 Western Line

The final contract model for the C5 work package is currently being determined.

The C5 work package includes the reconstruction of the Western Line rail corridor between Grafton and Kingsland stations. The works include constructing trenches and track slewing to enable grade separation of the Normanby Road crossing and for the new CRL connections. The works must be undertaken in stages to enable the Western Line to continue operating albeit with a period of single track running and a series of blocks of line. The key elements of the C5 work package include:

  • designing and constructing civil works including trenches, road overbridges, a rail overbridge, pedestrian footbridges, new platforms (excluding surface finishes behind the platform edge at Mt Eden), substructure for new station overbridge, lift and escalator pits and service relocations
  • designing and constructing the rail systems for the Western Line stage works including ballasted track, signalling systems staging, overhead catenary system and earthing and bonding
  • testing and commissioning of each phase of works with handback into operations
  • due to the operating environment, working with the rail infrastructure provider, KiwiRail, to ensure the practicality and acceptability of proposed work methodologies, possessions and continued operation etc
  • maintaining safe operational capability for continued passenger and freight services
  • undertaking works in accordance with a block of line process to be agreed with Auckland Transport and KiwiRail.

C6 Mt Eden Stormwater Relocation

C6 will be procured as a lump sum, construct only contract based on New Zealand standard conditions of contract.

The C6 work package has been identified to divert trunk utility services in advance of the C3 and C5 work packages. The scope of works includes the construction of a 1.95m diameter pipeline at depth below ground level replacing the existing pipeline length on a new alignment over approximately 420m between Water Street carpark and Ruru/Nikau street intersection in Mount Eden. The key elements of the C6 work package include:

  • boring and thrusting a new pipeline at depth on curved lines through a wide range of material with accurate level tolerances
  • demolition of two buildings
  • excavation and construction of three permanent access shafts at Water Street, Ruru/Nikau Street and near Road
  • joining of the new pipeline to the existing pipeline by cutting-in at both ends
  • minor utility relocations, vehicle access and retaining wall construction and relocating an overhead traction power gantry on the rail corridor.

C7 Systems, Integration, Testing and Commissioning (Systems ITC)

C7 will be procured using an Early Contractor Involvement (ECI) model engagement through a bespoke ECI agreement, with the design and installation work carried out under a form of D&C contract, and commissioning work carried out under a work package/management fee basis.

Works include provision of trackslab, track, overhead line, signalling (control software and systems and interlockings to be provided by CRLL), control systems, tunnel ventilation, fire strategy and communications systems, control room fit-out and building work, and trackside auxiliaries. Rail systems to be installed from the existing operational railway to the east of Britomart, through Britomart Station, C1, C2 and DSC, the new station and tunnels (C3), and to the Western Line (C5).

Works also include responsibility for Operational Readiness. Once construction work has been completed and individual systems have been tested and commissioned, the system needs to be commissioned into service. This will include a trial running period, equipment testing and commissioning, driver training, test train running and operating/maintenance manual updating. Key stakeholders will include construction contractors, the train operator (currently Transdev), KiwiRail as owner and network operator, AT and CAF (the train supplier).

^ back to top


C8 Wider Network Improvements

The final contract model for the C8 work package is yet to be determined.  The C8 work package may be carried out in stages, separately or as part of other work packages.

In order for the 2023 train plan to be achieved, an analysis of the network capacity, including modelling has been undertaken and has identified certain network enhancements that are required as a priority to deliver the targeted network timetable at CRL opening.  These network enhancements are to be delivered under the C8 work package. The key elements of the C8 work package include the following:

  • Newmarket crossovers
  • Henderson turnback platform
  • Otahuhu 3rd Platform
  • Otahuhu Loop Road
  • Strand Crossover

C9 Britomart East

The final contract model for the C9 work package is yet to be determined.

The C9 work package includes modifications within Britomart Station that are completed after trains are operating through CRL. The key elements of the C9 work package include:

  • refurbishment of the eastern entrance concourse
  • modifications to the affected mechanical, electrical, fire, communication and control accommodation
  • extension of the eastern concourse over the track
  • provision of additional vertical access at the eastern end of the station from platform level
  • the provision of additional emergency escape capacity to street level from the B1 concourse level
  • upgrade of the existing escalators at the eastern end of the station
  • the construction of the new island platform for terminating services to track realignment by the C7 contract work package.

^ back to top