|
|
|
|
|
|
| |
|
|
| |
|
Thank you and Merry Christmas from CRL |
| |
It’s been a year of great progress on the City Rail Link (CRL), with some important milestones reached.
CRLL chief executive, Dr Sean Sweeney, says building 3.45km twin tunnels and new stations up to 42 metres underground in the middle of a built-up city, is no small task, but he is delighted with the progress made so far.
“When building infrastructure of this size and scale in a busy urban environment, it’s impossible not to impact people in some way. We work hard to minimise the more negative aspects of our construction works but inevitably we do impact on people’s lives, whether they’re dealing with construction noise or having to take a detour around our worksite.
“On behalf of the CRL project team, I’d like to thank everyone for their support, patience and understanding as we work to complete the biggest transport infrastructure project ever to be undertaken in this country.
“When CRL opens in 2024, Aucklanders will have new world-class stations and a modern rail service that will benefit the entire transport network for decades to come. It will be worth the wait.”
|
| |
|
|
|
|
| |
|
|
| |
|
|
| |
|
Event marks CRL tunnel break-through |
| |
CRL celebrated a major milestone this month with the breakthrough from the Albert St trench to CRL tunnels built under the neighbouring Commercial Bay site.
The tunnels between the two sites meet under the Customs St traffic deck, which was built last year to keep traffic moving while the work is carried out underneath.
CRL’s CEO, Dr Sean Sweeney, added: “The nature of the excavation, the tight confines and the city centre location all make building this project extremely complex and I’m delighted with the progress we’ve made to date.”
CRL contractor Connectus JV can now complete the construction of the remaining third of the Albert St tunnel box. The backfilling of the trench will continue until it is completely covered – sometime in mid-2019.
|
| |
|
|
|
|
| |
|
|
| |
|
|
| |
|
CRL wins supreme sustainability award |
| |
CRL has been recognised for changing the way infrastructure projects are designed and delivered in NZ.
The project won both the Efficiency Champion category and the Supreme NZI Transforming New Zealand Award at this year’s NZI Sustainable Business Network Awards.
Rachel Brown, CEO Sustainable Business Network, says: “The CRL will be a tremendous part of Auckland’s public transport infrastructure. It will help demonstrate how New Zealand can move to a low carbon, circular and more accessible city. City Rail Link exhibits best practice that provides an excellent model for other businesses to follow.”
The project is on track to reduce greenhouse gas emissions associated with energy and material use during construction by over 4,000 tCO2e – the equivalent emissions of around 4,500 flights between Auckland and London - and has thus far diverted 97% of construction and demolition waste from landfill.
|
| |
|
|
|
|
| |
|
|
| |
|
Changes to Albert St layout in New Year |
| |
Some significant changes will be made to the layout of Albert St in the New Year.
At the southern end of the site, work will begin on reinstating the Wyndham St intersection. The struts (horizontal support beams) will be removed, the trench back-filled and the road surface reinstated by about March 2019.
From March, Albert St’s northbound traffic lane will move closer to the centre of street, onto the existing construction traffic deck, to enable the public realm reinstatement works to begin. Connectus JV will remove the pile capping beams before completing the backfilling of the trench and reinstating the road with tree pits, stormwater catchpits and new kerb lines.
CRL’s Albert St tunnel box is expected to be completed by about August 2019.
|
|
|
| |
|
|
| |
|
|
| |
|
More CRL tunnel breakthroughs early next year |
| |
Early next year, the CRL tunnel trench being excavated from Britomart Station’s Chief Post Office (CPO) building and Lower Queen St will connect to the underground rail tunnels that have been built across the Commercial Bay site.
This will provide a complete tunnel section from Britomart through to the Albert/Wyndham St intersection.
Excavation of all tunnel areas under the CPO building and Lower Queen St will continue over the Christmas/New Year period and concrete tunnel construction is expected to start in this location in January 2019.
Within the CPO building, contractor Downer Soletanche Bachy JV continues back-of-house preparations before the tunnels break through to Britomart Station early next year
|
|
|
| |
|
|
| |
|
|
| |
|
Jeffie the TBM starts Mt Eden pipe-jack next month |
| |
‘Jeffie’ – the micro tunnel boring machine that will install a 420-metre section of replacement stormwater main through Mt Eden – is expected to start her pipe-jack journey in early January.
The existing stormwater main lies in the path of the future CRL tunnels at Mt Eden, so must be diverted before work can begin on building the new station and twin tunnels in the area.
On Wednesday this week, Jeffie was lowered into the 17-metre-deep launch shaft on Water St, where her final preparations are being made. She will simultaneously tunnel and install new concrete pipe segments and is expected to arrive at CRL’s reception shaft on Nikau St by April next year.
|
|
|
| |
|
|
| |
|
|
| |
|
St Barbara’s Day ceremony for Jeffie and workers |
| |
A special ceremony was held for Jeffie on 4 December – also known as St Barbara’s Day. St Barbara is the patron saint of miners and tunnellers – so it was an auspicious day to hold the event.
A statuette of St Barbara was carried by March Bessac Joint Venture (MBJV) tunnel supervisor Laurent LeCalvez into the Water Street, where Jeffie will start her pipe-jacking work.
It’s traditional when a new project starts for a small shrine to St Barbara to be set up at the tunnel entrance, followed by a dedication and an invocation to St Barbara for protection of the workers.
|
| |
|
|
|
|
| |
|
|
| |
|
Ground investigation works to begin in Mt Eden |
| |
Geotechnical investigations will be undertaken in the rail corridor at Mt Eden over the Christmas break.
The work involves drilling boreholes and undertaking cone penetration testing to better understand ground conditions. The results will assist CRL engineers with the design of the physical structures that are needed to connect the new CRL line with the existing Western Line track at Mt Eden.
The daytime works are scheduled to take place from 27 December to 5 January to coincide with KiwiRail’s Christmas/New Year maintenance schedule, when the rail line is closed to trains and overhead electrified wires turned off.
The investigations are taking place at various locations, from just east of the Normanby Rd rail crossing to the Mt Eden Station side of Porters Ave.
|
| |
|
|
|
|
| |
|
|
| |
|
|
| |
|
CRLL announces single alliance |
| |
CRLL has announced that it intends to proceed with a single alliance to deliver the stations, tunnels and rail systems – including the C7 Rail Systems contract.
CEO Dr Sean Sweeney says that a single alliance will deliver positive outcomes and significant opportunities for the project.
The decision follows the announcement that RCR Tomlinson and more recently RCR infrastructure (NZ) had gone into voluntary administration. RCR Infrastructure (NZ) Ltd forms part of the Systems Alliance (C7 consortium) that has been awarded the Interim Project Alliance Agreement (IPAA) that is currently delivering the design for the C7 Systems Contract.
“We have determined that the best-possible response is for the current C7 consortium to continue to deliver the design elements for the C7 systems. However, they will no longer submit a tender for the C7 construction works which will instead be incorporated into the C3 Main Station and Tunnels Alliance - due to start construction mid-next year.”
Dr Sweeney says that delivering CRL on schedule is a key priority and was a critical factor in deciding to go with a single alliance.
|
| |
|
|
|
|
| |
|
|
|
|
|
|
|
|
| |
City Rail Link Ltd
Private Bag 105777, Auckland 1142, New Zealand
This email was sent to {EMAIL}
You received this email because you are registered with City Rail Link
|
| |
Sent by
|
| |
|
|
|
|