City Rail Link
Albert changes 4 Feb 2019 2.jpg

Construction: Albert Street - Upper Area

CONSTRUCTION: ALBERT STREET - UPPER AREA

This page details work in the upper Albert Street area including between Wellesley and Victoria Streets -followed by the latest notifications.

Our Albert Street works – also referred to as Contract 2 (C2) - are being undertaken by Connectus, a McConnell Dowell and Downer joint venture.

C2 started with the relocation of a major stormwater line in Albert Street between Swanson and Wellesley Streets and the strengthening and bridging of a section of the Orakei Sewer Main at the intersection of Victoria Street and Albert Street.

Since then, Connectus has also completed a ‘cut and cover’ trench down the middle of Albert Street between Wyndham Street and Customs Street and has almost finished building the twin underground rail tunnels inside it.

Canopy removal works between Victoria & Wellesley Streets

Connectus is also responsible for a separate portion of work that involves the removal of canopies from four buildings (AA, Manhattan Apartments, SkyCity and Auckland Council) located on the western side of Albert Street between Victoria and Wellesley Streets.

These canopies must be removed to provide future access for a large piling rig to install the 20-metre-long piles that will provide ground support for the new Aotea Station. The canopy works are expected to be completed in about October 2019.

Link Alliance Early Works

A single Alliance is delivering the main CRL works - the stations and tunnels. City Rail Link and the Link Alliance negotiated a $75m Early Works Contract.

There will be utility investigations and diversions starting at the Wyndham Street end of Albert Street. They will be completed in stages from September 2019 until mid-2020.

Seven canopy removals will take place between December 2019 until Q2 2020. These will be at various locations along Albert Street and at the corner of Victoria and Wellesley Streets.

In December 2019, we’ll establish a work site in the Bledisloe car park at the rear of the Auckland Council offices. An area of carparks will be retained for council customers.

Piling and D-wall construction for the Aotea Station- ground support starts Q2 2020.


TIPS FOR VIEWING THE POSTERS BELOW

  • To see them full screen, press on the square symbol at the bottom right of the box.

  • The poster then opens in a new tab. Press the escape key to return to this page.

  • To download, when you view full screen, depending on your browser, there is an arrow at the top left of the screen - click on that.

Introduction to the City Rail Link

Aotea Station main works

Albert Street utility diversions

Utility investigations

Tunnels and Stations

The Link Alliance

Meeting with the local community


Location of utility investigations

Below are indicative locations of trial trenches to investigate service locations. Small work areas will be set up at each location to complete the works.

Utility investigations

  • About 12 investigations are needed between Wyndham and Wellesley Streets to pinpoint the location of existing underground utility services to help design their relocation ahead of the construction of the new Aotea Station.

  • By confirming our assumptions about where exactly those utilities lie, we de-risk the utility diversion works by providing a safer and more robust design for our contractors.

  • At each of the locations, there will be about two days work.

  • We anticipate there could be some noise from the concrete cutting, minor excavations and Hydrovac machines which suck the material from the services.

  • Noise mats will help buffer the ground-floor businesses and pedestrians from that work-related noise.

Utility diversions

We need to divert utility services because:

  • Some services clash with the alignment of the piles that will support the station structure

  • There is insufficient space for utilities infrastructure between the underground roof of the station and road level

  • It’s safer to excavate and construct the station with all the utility services out of the way.

Managing the utility diversions

  • These diversions can be noisy and disruptive so we will work to manage any negative impacts as practicably as possible.

  • Property access will be maintained. However, there may be times when we need to liaise with businesses about the timing of works to minimise any disruption such as at weekends or evenings.

  • There may be times pedestrians need to be re-routed around works happening on the footpaths.

  • We will use water-filled barriers and temporary fencing wherever possible to maintain visibility for businesses.

Management plans

  • A suite of management plans are required by the CRL designation and the regional resource consent to manage the effects of construction.

  • The management plans are developed by subject matter experts on areas such as traffic, access and parking, noise and vibration, social impact and business disruption, air quality, contamination and trees and vegetation.

  • The plans will undergo an independent peer review and be lodged with Auckland Council. We hope this will be finished by the end of August so we can start the relocation works.

  • Consent documents related to this area, once approved, can be seen here.

^ back to top


Latest Notifications

Update on utility work

03 September 2019



Consent plans can be found at this link below


Contact

If you have any questions or concerns about the Link Alliance works, please email aotea@linkalliance.co.nz or phone 0800 CRL TALK and press 3. For the Albert St work between Customs and Wyndham Street, please press 2 to talk to those contractors, Connectus.