City Rail Link
media_releases_2_web.jpg

Media Releases

MEDIA RELEASES

Below on this page are the latest news releases issued in 2019.

News releases from 2018 and 2017 can be found here.

Earlier CRL-related releases from the AT CRL Project Team, New Zealand Government and Auckland Council can be read here.


Revised cost for transformational City Rail Link

17 April 2019

City Rail Link Ltd (CRL Ltd) today announced a revised cost envelope for completing the entire Auckland City Rail Link project totalling $4.419 billion, alongside naming its preferred bidder for its substantive C3 Contract to build the underground tunnels and stations and a $75 million Early Works Contract.

CRL Ltd’s Chief Executive, Dr Sean Sweeney, says after a rigorous and comprehensive review of project costs, a revised cost envelope has been submitted to the project’s sponsors – the Crown and Auckland Council - for approval.

“The $1 billion cost increase on the previous $3.4 billion estimate made in 2014 reflects significant changes impacting the project in the past five years,” says Dr Sweeney.

“No-one could have foreseen the competitive pressures that have occurred in the construction industry over the past few years and the impact that has on costs, particularly for a project the scale and complexity of the City Rail Link.

“Eighteen months ago, the value of work in the infrastructure pipeline on both sides of the Tasman was $80 billion – the value of that work is now estimated at $230 billion.

“Last year, a decision was made to increase the scope of the project to accommodate longer, nine-car trains at stations. Planning today for a city that will be much bigger in the future reinforces the benefits the City Rail Link City will deliver to the way people travel, work and live in Auckland.

Other factors contributing to the revised cost envelope are higher escalation, or construction inflation costs, and an increase in the contingency risk allowance for any future unplanned events.

“Put together, they have all helped add costs to the project overall. Keeping a growing city moving is a serious challenge, but when we complete the City Rail Link it will double the number of Aucklanders within 30 minutes travel of the CBD.”

Dr Sweeney says CRL Ltd’s own cost review underwent a rigorous examination by two international assessors to ensure the project delivers the best value for money for Aucklanders.

Decisions by the Crown and Auckland Council regarding their endorsement of the revised cost envelope are expected in early May.

After an exhaustive competitive tender process, the Link Alliance (Vinci Construction Grands Projet S.A.S,, Downer NZ Ltd, Soletanche Bachy International NZ Limited, WSP Opus (NZ) Limited, AECOM New Zealand Limited and Tonkin + Taylor Limited) has been announced as the preferred bidder for the C3 contract – the project’s largest package of work.

The Link Alliance was one of two groups of New Zealand and international infrastructure companies that submitted what Dr Sweeney, describes as “world class and competitive bids” for the contract. The other group was a consortium of: CPB Contractors Pty Limited, UGL (NZ) Limited, Beca Limited, Jacobs New Zealand Limited and McMillen Jacobs Limited.

Dr Sweeney says that both these joint-ventures consists of outstanding contractors with a wealth of experience delivering major project both here an overseas.

“The calibre of both the tenders were exceptional. Aucklanders can be confident that the project will be delivered to a high standard leaving behind an outstanding legacy for the city,” he says.

Dr Sweeney says progress on the project will still continue at pace as CRL Ltd starts negotiations with the Link Alliance to deliver the $75 million Early Works Contract over a three-month period. The contract includes work relating to design, consents, permitting, utilities and mobilisation.

“The project is already well underway at Lower Queen Street/Britomart, Albert Street and Mt Eden, and momentum will continue. CRL Ltd will now work with the preferred bidder to get the Early Works Contract underway as quickly as possible.

“This keeps us on track to have this transformational project in place and delivering significant benefits for Aucklanders at the end of 2024.

“Today’s announcements represent huge step forwards for a project that will create accessibility and development opportunities that will allow Auckland to remodel itself as a city that is proudly international,” Dr Sweeney says.  ENDS 

Frequently Asked Questions

Why was the Link Alliance selected as the preferred bidder?

Two, tier-one consortia submitted world-class proposals to deliver CRL’s largest construction package, C3 main stations and tunnels.

Those proposals were evaluated through a rigorous and competitive tender process to get the best outcome for Aucklanders.

Both consortia bring a wealth of experience both internationally and in New Zealand and have the skills and means to deliver a project of this scale and City Rail Link could not be more pleased to have two such high calibre proposals.

The Link Alliance was selected on the basis of a strong proposal that offered an experienced construction management team, significant commitment to the Alliance from the Executives of the construction firms involved. An efficient construction methodology and innovative engineering ideas.

The Link Alliance brings a phenomenal amount of experience delivering major projects including:

  • NZ Transport Agency: Memorial Park Alliance Projects

  • MTR Hong Kong: Shatin to Central Link 1103

  • Qatar Railways Company: Doha Metro – Red Line South

  • Qatar Railways Company: Lusail Light Rail Transit, Contracts 1&2

To have two such exceptional bidders in today’s climate where the pipeline of infrastructure work is so extensive, is testament to the benefits that this project will deliver and the readiness for it to proceed to the next stage.

What is the contract that CRL Ltd has signed with the preferred bidder?

At this stage no contract has been signed and there are still a number of processes to go through before a contract award recommendation.

CRL Ltd will continue to resolve several commercial matters before the Contract Award Recommendation for C3 is announced in May, subject to all necessary approvals from the project’s Sponsors – the Crown and Auckland Council.      

In the meantime, to ensure project momentum continues, CRL Ltd will enter into an Early Works Contract with Link Alliance to carry out design, permitting, utilities and mobilisation works on the contract. The Early Works Contract is valued up to $75m.

While the Early Works Contract is not a commitment to carry out the full C3 contract, it is recognition that Link Alliance is the preferred contractor for C3.

What does the C3 Contract include?

The C3 (main stations and tunnels) contract is the largest of all the CRL contract packages. It includes construction of twin rail tunnels, construction of two underground stations and rebuilding Mt Eden station.  The City Rail Link is the largest infrastructure project undertaken in New Zealand.  

Why is the revised cost envelope higher?

The revised cost envelope reflects higher costs in four key areas: 

  • Contingency and escalation costs ($310 million)

  • Construction costs ($327 million)

  • Accommodating longer, nine-car trains ($250 million)

  • Non-direct cost ($152 million) 

The cost of the City Rail Link project was last estimated in 2014 and there has been significant change since that time.

The construction climate has experienced a significant increase in demand. Less than two years ago, the infrastructure pipeline in Australasia valued approximately $80 billion, whereas it is now valued at approximately $230 billion.

This is particularly evident in Auckland, where there are currently 98 cranes in the city – more than any city in the USA.

This kind of climate has significant impact on constructor availability and appetite for projects and risk as well as things like escalation.

In 2014 the project assumed an escalation of two percent.  New Zealand is now experiencing escalation of more than six percent and will do so for the foreseeable future.

Allocation for contingency on the project was underestimated when the project was last estimated in 2014, an independent audit concluded that contingency on the City Rail Link project was below international benchmarking.

Changing the scope and future proofing the project to allow for Auckland’s growth and projected increase in passengers numbers, together with the establishment of City Rail Link Ltd as a Crown Entity, also contribute to the revised cost envelope.

Stations at Mt Eden, Karangahape Road and Aotea in the central CBD are being designed for longer, nine-car trains to allow up to 54,000 people to move in and out of Auckland’s CBD during the rush hours – the equivalent capacity of three Auckland Harbour Bridges or 16 extra traffic lanes.  The original scope allowed for 36,000 people at peak times.

Creation of CRL Ltd – with the Crown and Auckland Council has the project’s sponsors – incurred set-up costs not included in the 2014 estimate.

What are the next steps? 

City Rail Link Ltd has submitted the revised cost envelope to its sponsors. The project’s two sponsors – the Crown and Auckland Council – will now consider that cost through their processes. A decision regarding their endorsement is expected in early May.

In the meantime, CRL Ltd and the Link Alliance are negotiating the $75 million Early Works Contract and expect work on that to get underway quickly.

CRL Ltd will continue to resolve several commercial matters before the Contract Award Recommendation for C3 is announced in May, subject to all necessary approvals from the project’s Sponsors – the Crown and Auckland Council.

Statement issued by Mayor of Auckland, Phil Goff

Auckland Mayor Phil Goff has said that tighter financial management will help fund an additional $500 million requested by City Rail Link Limited (CRLL) for construction of the transformational underground rail project.

The Mayor’s comments are in response to CRLL requesting from Council and Government additional funding of $1 billion (split 50/50) after announcing that the Link Alliance is the preferred bidder to deliver the new stations, tunnels and rail systems.

Mayor Phil Goff said, “The City Rail Link (CRL) is a critical part of the changes we are making to reduce congestion and ensure we can move around our city.

“The CRL doubles the capacity of rail through Britomart and in peak hour will have the capacity to carry up to 54,000 passengers.

“The CRL will significantly reduce travel time from the West and the South,” Phil Goff said.

“The cost of the tunnels and underground stations, two of the biggest parts of the project, was determined by a competitive tender process. The increased cost estimate reflects the increase in demand and costs for major construction projects across Australasia.

“A significant part of the cost increase, some $250 million, reflects the need to future proof the tunnels and stations. We won’t repeat the mistake of the Harbour Bridge which was built at half of the size it needed to be, and had to have major additions made to it within eight years.

“The additional cost to Council will not involve higher rates for Aucklanders and it will be met without breaching the debt to revenue limit on Council borrowing.

Funding of the CRL is met jointly by Council and Government on a 50/50 basis.

Mayor Phil Goff says, “It is unfair for Aucklanders to meet half the cost of the CRL when no other part of the country has to do so and I’ve argued that case to Government. The Government has refused to revisit the deal saying that was what was agreed between the previous Auckland Council and National Government.

“However, Government has agreed to phase the timing of Council’s contribution to enable it to work within the constraints of its budget.

“Council will make changes in financial management that will enable it to keep under its debt to revenue ratio. It will benefit from current lower market interest rates. Council will also dispose of some non-strategic assets including some parking buildings.

“The Governing Body of Council has been advised of options to meet the increased costs and will consider those options before making a decision in May,” Phil Goff said.

“The CRL project is the biggest investment Council is making in transport infrastructure in the next few years.

“Providing additional funding to CRLL will require careful management of Council spending. Council will continue to pursue efficiency and value for money initiatives, and take a conservative approach to new spending,” Phil Goff said.

^ back to top


Ōtāhuhu improvements start for City Rail Link

10 April 2019

KiwiRail is starting to build a new section of rail line to the third platform at Ōtāhuhu Station in Auckland’s south as part of wider rail infrastructure improvements to prepare the network for the City Rail Link.

Over the next 11 months, KiwiRail will construct the new 1.3-kilometre-long section of track alongside the main line, four new cross-overs to allow trains to switch between tracks, and new overhead line and signal equipment between Ōtāhuhu Station and Portage Road.

The work will allow a third platform to be used at Ōtāhuhu Station for improved train services when the City Rail Link opens in 2024.

The start of work is welcomed by City Rail Link Ltd’s Chief Executive, Dr Sean Sweeney.

“It’s another important step forward for the City Rail Link and the huge changes it will make to allow people to travel around the city more easily,” he says.

KiwiRail’s acting Chief Executive, Todd Moyle, says KiwiRail is proud to create stronger connections through a modern and more efficient transport network for Auckland.

“KiwiRail keeps cities moving, connects workers to cities sustainably and enables 34 million low-carbon commuter journeys each year.”

“We have ambitious plans for New Zealand’s transport future and the City Rail Link is part of this,” Mr Moyle says.

The Ōtāhuhu improvements will support better services for people travelling between Auckland’s south and west when the City Rail Link opens.

KiwiRail staff and its contractor, Total Rail Solutions, will deliver most of its Ōtāhuhu works during weekday business hours. Some work will be completed during weekends and public holidays when there are no trains running and the overhead lines are shut off.

Auckland Transport will upgrade Ōtāhuhu Station.

The Ōtāhuhu works are the latest in a series of upgrades on Auckland’s rail network connected to the City Rail Link.  Upgrades were completed at The Strand in Parnell earlier this year, and other work is planned at Henderson and Newmarket.

The City Rail Link includes construction of twin 3.45-kilometre-long rail tunnels between the current dead-end station at Britomart in the CBD and the existing Mt Eden station on the Western Line, and two underground stations.

It is the largest transport infrastructure project ever undertaken in New Zealand and when it opens it will double the capacity of the Auckland’s rail network to carry up to 54,000 passengers an hour at peak times.

^ back to top


Auckland network prepares for City Rail Link

01 March 2019

City Rail Link Ltd (CRLL) and KiwiRail today celebrated the completion of the first set of wider network improvements required to support Auckland’s transformational City Rail Link when it opens in 2024.

KiwiRail, on behalf of CRLL, has installed a new track cross-over point and other upgrades in The Strand area of the Auckland network, one busiest sections of rail in the city. Over five months, KiwiRail installed the cross-over, and modified the track and overhead lines and signal equipment. The work was completed in intensive blocks, to reduce the impact on neighbours and commuters.

KiwiRail acting Chief Executive, Todd Moyle, a new track layout was required to simplify access to The Strand stabling yard - the area where morning peak services are ‘stabled’ before they come back into service for the evening peak. Over 300 trains travel through this area daily.

“KiwiRail is proud to contribute to a more reliable and resilient rail service for Aucklanders as we continue building stronger connections for a better New Zealand.

“Once the City Rail Link is open and operating, more trains will travel in and out of the city more often. Wider network improvements are required to ensure the increased timetables can be achieved, Mr Moyle says.

CRLL’s Chief Executive, Sean Sweeney, says the Strand is the first construction project to be completed from a huge programme of work for a project that will have a huge impact on the way Aucklanders travel around their city.

“Just as significantly, it is also the first collaborative piece of work undertaken by KiwiRail and City Rail Link Ltd. We look forward to continuing this relationship on network improvements at Otahuhu later this year.

“Together CRLL and KiwiRail have demonstrated how well we can work together on work like this, and the wider importance of collaboration as delivery of the City Rail Link starts to ramp up,” Dr Sweeney says.

CRLL is currently evaluating two bids to design and construct twin 3.45 kilometre-long rail tunnels below Auckland’s CBD, two underground stations, the upgrade of a third station, and the installation of track and signalling, safety and communication systems.

The City Rail Link is the largest transport infrastructure project ever undertaken in New Zealand.

^ back to top


Latest section of Auckland rail link taking shape

08 January 2019

Construction of Auckland’s City Rail Link has taken another significant step today with work starting on construction of the first of the two rail tunnel boxes to be built under the heritage-listed Chief Post Office (CPO) building in lower Queen Street.

Seventy cubic metres of reinforced concrete is being poured for the first base slab, or some of the floor, of the northbound tunnel below the old building.

Britomart pour 3 08 Jan 2019.PNG

This pour was an important moment for City Rail Link Ltd (CRLL) and its Contract 1 (C1) contractor Downer Soletanche Bachy JV, says CRLL Chief Executive Dr Sean Sweeney.

“We’ve been working for this moment since July 2016 – for the past 30 months or so, this is what we have been gearing up for. That time has been a challenging one for our C1 contract in lower Queen Street and Britomart. Our teams have been working in some pretty demanding conditions, not only immediately adjacent to a live railway station but also excavating below sea level with the Waitemata Harbour only a few metres away. On top of that, some remarkable skill and innovation has been used to protect the CPO building so that we could get underneath it.”

Dr Sweeney says there is still a lot of work to be done in this area before both the northbound and southbound tunnel boxes are completed later this year.

“Once we’ve finished, it will be possible to walk the first section of the City Rail Link from Britomart station to beneath Albert Street as far as Wyndham Street. As for the CPO building, we are on track to reinstate and return it as part of the Britomart station in late 2020.”

The 3.45-kilometre-long underground City Rail Link between Britomart and Mt Eden will be completed in 2024.

^ back to top