Albert St tunnel boxes

Tunnel box construction under Albert St is almost complete, with CRL contractor Connectus targeting having the last roof sections complete by the end of July this year.

Tunnel floor and tunnel walls are largely complete. Only four more sections of the roof need to be poured, and then we’ll be able to complete the backfilling under Customs St.